On 25 October 2026, the Supreme Court-appointed receiver handed possession letters to 51 buyers at Amrapali Leisure Valley after a 14-year ordeal, while 86 other developer insolvencies across northern NCR remained unresolved in tribunals, as reported by [ET Realty](https://realty.economictimes.indiatimes.com/news/residential/buyers-get-possession-letters-for-amrapali-project-as-86-others-remain-stuck-in-nclt/135185815). While Section 12 of the Insolvency and Bankruptcy Code (IBC) mandates a strict 330-day outer ceiling for Corporate Insolvency Resolution Processes (CIRP), practical resolution cycles routinely average 630 to 750 days. Once the National Company Law Tribunal (NCLT) admits a petition under Section 7, 9, or 10, Section 14 imposes an absolute moratorium halting all RERA and consumer forum enforcement. Bengaluru buyers must screen developer entities on public NCLT registries and verify RERA quarterly filings before paying token advances.
Those 86 projects are not in Bengaluru. The wait is the lesson. A handover that a buyer described as nearly 14 years in the making is not a date you can put on a home loan.
What did the 25 Oct report actually say?
Abhijay Jha, TNN, published the piece at 12:46 PM IST on 25 Oct 2026. On the preceding Friday, Supreme Court-appointed receiver R. Venkataramani handed no-objection certificates and possession letters to 51 buyers in towers A1, G1 and H1 at Phase 1 of Adarsh Awas Yojana, Amrapali Leisure Valley. The project has eight towers. NBCC said keys for those buyers were proposed within 30 to 45 days.
The same story said 86 other projects across Gautam Budh Nagar and Ghaziabad were still in insolvency, a decade after the Code came into force in 2016. Fifty-six are in Gautam Budh Nagar and 30 in Ghaziabad. The count covers residential and commercial schemes. Some have sat there since 2019.
Dipankar Kumar, a buyer in the project, put his wait at nearly 14 years. He said Ultra Homes approached the tribunal in 2017. The report dates the amendment that treated allottees as financial creditors to 17 Aug 2018, and Pioneer Urban, which upheld it, to 9 Aug 2019. His line that the Court cancelled the companies' RERA registrations is his account. This page has not read that judgment. The story has no Karnataka count and no recovery figure. Do not invent either.
Why does a 330-day law still leave people waiting?
Section 12 says the corporate insolvency resolution process shall finish within 180 days of the insolvency commencement date. The resolution professional may seek one extension, and the tribunal may add not more than 90 days. A proviso inserted in 2019 says the process shall be completed within 330 days, including any extension and the time taken in legal proceedings. (Insolvency and Bankruptcy Code)
Sumit Khanna, quoted in that report, said a case ending in an approved plan takes 633 days on the regulator's count, and closer to 750 from admission to approval. He said three-quarters of current NCLT cases have run past 270 days, that admission has routinely taken a year or more, and that the tribunal has worked with 52 members against a sanctioned 63. Those are his figures, as printed, not a download from the regulator. NBCC's 30 to 45 days is a proposal for keys. It is not the length of the case.
UP RERA chair Sanjay Bhoosreddy told the paper that a project in the NCLT leaves his authority's jurisdiction. That is not a Karnataka order. Section 14 is what you can read: a moratorium bars new suits and pending proceedings against the company, including execution, and bars the company from transferring its assets, until the process ends. Whether your K-RERA file is caught is a question for your lawyer.
The explanation to section 5(8)(f) treats money raised from an allottee as a financial debt. That label is not a handover date. Allottees who want to start the process file together: at least 100 of the same project, or at least 10% of them, whichever is less (section 7(1)). One buyer cannot go in alone. While no moratorium is running, section 18 is still the delay remedy, worked in the guide to refund or interest under section 18. If a case is already admitted, ask which forum is open. A shorter account of the rights is in builder insolvency and homebuyer rights.
What to check in Bengaluru before the token
The Amrapali letters are a finish line for 51 people. Your check is at the start.
Open the project on rera.karnataka.gov.in and read the promoter, the end date and the complaints list. The clicks are in how to check any Bengaluru project on RERA Karnataka. A complaints row is a file, not a score. Then email the company on the draft agreement: has any application under sections 7, 9 or 10 been filed or admitted against that company, or against the landowner on a joint-development share? "No case" on a phone call is not an answer. You want the name as it would appear on a cause list, and a yes or no.
Search that name yourself. The public cause list and the orders are the record. A lawyer can go further, into eCourts and the charges. The wider background pass sits in how to judge a developer before booking. Do it before the token.
Two money rules still apply while the project is an ordinary RERA project. The promoter must keep 70% of the amounts realised from allottees in a separate account, for land and construction (section 4(2)(l)(D)). The promoter cannot take more than 10% of the cost before a registered agreement for sale (section 13). A stall does not repeal either section. It is a reason to see which account your cheque names.
| Question before you pay | Where the answer should be | Walk away signal |
|---|---|---|
| Who receives the money? | The same company on the RERA page, the draft and the cheque | A different entity "for convenience" |
| Is a case already admitted? | A written reply, plus your own look at the orders | "It will be withdrawn", or silence |
| What is the RERA end date? | The project page, not the brochure | A date already past, with no extension order |
| Are complaints pending? | The list, then the order, not the status word | A headline with no PDF behind it |
| Where does the 70% sit? | The account named for this project | A personal account or a group account |
| Is the advance inside section 13? | 10% or less until the agreement is registered | A larger sum "to block the unit" |
None of those day-counts is a forecast for a tower in Bengaluru. A desk that says buyers "got their flats" is using 51 letters to cover 86 projects the same article left in the tribunal. If you already own and you hear the word insolvency, keep every receipt and do not sign a revised plan on the spot.
Before any token on a Bengaluru project, do this evening's work: open the Karnataka RERA page, copy the registered end date and any extension, save the latest quarterly update with its "as on" date, and search the same promoter's other projects for slipped dates. A possession-letter story from another state, or a desk that says buyers "got their flats", does not replace that file. If any line is already late, or the update is a year old, do not pay to "block the unit" above the section 13 cap.
Checklist
Related reading
Frequently asked questions
No. The 86 are in Gautam Budh Nagar and Ghaziabad, 56 and 30, as TNN reported. There is no Karnataka count in the piece. Use it as a picture of how long a tribunal case can run, then check the company in front of you.
The explanation to section 5(8)(f) deems money raised from an allottee to have the commercial effect of a borrowing. The report dates that amendment to 17 Aug 2018 and the decision upholding it, Pioneer Urban, to 9 Aug 2019. The status puts you in the creditor class. It does not set a date for the keys.
Not under the second proviso to section 7(1), if you are an allottee. The application is filed jointly by at least 100 allottees of the same project, or at least 10% of them, whichever is less. Other creditors have their own routes. A lawyer should say which one, if any, fits.
Section 14 bars new suits and the continuation of pending proceedings against the company, including execution, once the moratorium starts. UP RERA's chair told TNN that a project in the NCLT leaves his authority's jurisdiction. Whether your K-RERA file is covered is a legal question on the complaint you filed. Ask before you pay a fresh fee.
Section 12 says 180 days, one extension of up to 90 days, and a cap of 330 days including time in court. Khanna told TNN that cases ending in an approved plan have been taking longer than that cap. The buyer in the same report described a wait of nearly 14 years before letters in October 2026.
Lawyer note: This page is general information from a news report and the text of the Code. It is not advice on a case. Insolvency, the moratorium and a RERA complaint turn on the company, the date of admission and the forum. Have a property lawyer read your papers before you pay or file. Checked 17 Nov 2026.
Sources
Checked 17 Nov 2026.
-
TNN, Abhijay Jha, ET Realty, 25 Oct 2026. Letters for 51 buyers, 86 projects still in insolvency, Khanna's day-counts, tribunal strength, and Bhoosreddy on jurisdiction: https://realty.economictimes.indiatimes.com/news/residential/buyers-get-possession-letters-for-amrapali-project-as-86-others-remain-stuck-in-nclt/135185815
-
Insolvency and Bankruptcy Code, 2016, sections 5(8)(f), 7(1), 12 and 14: https://www.indiacode.nic.in/bitstream/123456789/15479/1/the_insolvency_and_bankruptcy_code%2C_2016.pdf
-
Real Estate (Regulation and Development) Act, 2016, sections 4(2)(l)(D), 13 and 18: https://www.indiacode.nic.in/indiacode/bitstream/123456789/2158/1/A201616.pdf