The Petroleum and Natural Gas Regulatory Board (PNGRB) authorises GAIL Gas Limited to construct city gas distribution networks across Bengaluru Urban and Bengaluru Rural districts. However, regulatory authorisation does not ensure immediate infrastructure at your layout. GAIL's prescribed installation pipeline requires a preliminary feasibility survey, civic street-cutting clearances, vertical building risers through approved utility shafts, and individual apartment metering. Registration on the GAIL portal is free of charge, with published tariffs specifying a refundable, interest-free ₹4,000 connection security deposit and a ₹500 consumption deposit. Piped gas infrastructure operates under an entirely separate statutory regime from BESCOM electricity metering and BWSSB water connections.
A new kitchen can have a hob on the brochure and a cylinder on the floor. The gap is the network. This page is only about piped natural gas. Permanent power is a BESCOM file. Water is a BWSSB file. Do not let one office's receipt stand in for the other two.
Who is allowed to lay the pipe
City gas is licensed area by area. On the Petroleum and Natural Gas Regulatory Board's entity list, opened 8 Nov 2026, the row for Karnataka's Bengaluru Rural and Urban districts names GAIL Gas Limited, and points to gailgas.com/operation/bengaluru. That is the authorisation. It does not say every street in Anekal, Whitefield or Yelahanka already has a main.
We could not read a ward-by-ward coverage map on that operations URL on 8 Nov 2026. The check that remains is the one in GAIL's own installation steps: a survey of whether a connection is feasible at that building. If the survey says the main has not reached you, the honest result is a cylinder until it does. A sales promise that "PNG is coming with the OC" is not the survey.
The application page tells a prospect to collect a form from a GAIL Gas site office or a direct marketing associate, or to register online at customer.gailgaspng.com. An application number is generated on registration. A business-partner number follows document checks. Keep both numbers. A verbal "you're on the list" from the builder's site office is not either of them.
What has to exist in the building
GAIL's installation sequence, on the same procedure page, is short and in this order.
First, a survey of feasibility. Second, laying the medium-density polyethylene pipe after permissions from the civic authorities. Third, vertical piping to the customers who have registered. Fourth, fitting and testing the galvanised-iron or copper pipe and the meter. Only then does the page move to converting an LPG stove and activating the supply.
Read that as four physical facts, not as a slogan. The street main needs a civic permission. The riser needs a route through the common shaft. The meter needs a place that can be read. The stove you already own may still be an LPG stove until someone converts the burners.
In a new apartment the builder often offers the shaft as a finished fact. Ask to see it on the sanctioned plan, and ask who has allowed the pipe through the common areas. The procedure page does not publish a form titled "society NOC". It does say the street pipe waits on civic permissions, and that vertical piping is laid to registered customers. If the association, or the builder while the association does not yet exist, has not agreed a route, the riser stops being a kitchen detail and becomes a building argument. Get that agreement in writing before you pay a deposit for a connection that cannot be piped.
Do not light a hob because the pipe looks connected. Activation is the last step on GAIL's page, after fitting and testing. Until they turn the supply on, the outlet is not a gas point you should test yourself.
What the published page charges
The procedure page says GAIL Gas is not charging any amount for registration. The security-deposit lines under it are less tidy, and they are not labelled as a Bengaluru-only tariff. This is what the page lists:
| Line on the procedure page | Figure | What to confirm |
|---|---|---|
| Registration | No charge | That the person collecting cash is not adding one |
| Reduction on the connection security deposit | ₹1,000 | Whether this reduction applies to your building |
| Connection security deposit, before supply starts | ₹4,000, refundable, interest free | The demand note for your flat |
| Deposit towards gas consumption | ₹500, refundable, interest free | The same demand note |
| Name transfer, except on death | ₹250 | Whose name is on the meter today |
| Stove conversion, LPG to PNG or the reverse | ₹50 a burner; ₹300 for a four-burner stove with oven and grill | Whether the builder's hob was already converted |
Confirm the payable figure on the application for your address before you transfer money. A national procedure page can lag a local scheme, and the ₹1,000 reduction line sits next to the ₹4,000 line without a worked example. Pay against a receipt that names GAIL Gas and your application number. Do not pay a site supervisor in cash for "the gas deposit" with no receipt.
A domestic rate per standard cubic metre is not on the procedure page we opened. A developer blog has quoted a Bengaluru rate elsewhere. We are not using that number. Ask GAIL, or read the bill of a neighbour who is already metered, and keep the bill. A rate that is not on your connection papers is not a cost you can plan.
The after-sales table also prices later work: removing a riser for a renovation at ₹250 a removal, refitting internal pipe at ₹350 a metre with a minimum of ₹500, disconnection at ₹100 and reconnection at ₹100. Those are not the new-connection deposits. They matter if someone tells you the kitchen will be "shifted after handover" and assumes the pipe moves for nothing.
Whose name should be on the meter
The documents the procedure page asks for are an identity proof and a proof of ownership. The ownership examples on the page are a sale deed or agreement, a rent agreement, an electricity bill, a BSNL bill, or a society certificate. In a new flat you may not have a sale deed in your name on the day you get the keys. You may have a possession letter and an agreement. Ask which of those GAIL will accept for your building, and get the answer from GAIL, not from the person handing over the keys.
If the builder or the association registered the connection in a company name, you want a transfer. The same table lists name transfer, except on death, at ₹250. That is a small number next to a deposit, and it is the number that tells you a transfer is a real step with a fee, not a favour. Do it while you are collecting the other post-registration papers. The order of khata, tax and utilities in the weeks after registration is set out in our note on the first 90 days. Gas sits in that pile. It does not replace the khata.
Two neighbours in the same tower can be in different positions. One stack may be on the riser. Another may still be waiting for the vertical pipe. Ask for your flat number on the registration, not "the project has PNG".
Power and water stay on their own desks
A possession folder often arrives as one plastic sleeve. Split it.
Permanent electricity for a new flat is the subject of our answer on BESCOM power before handover. This page does not repeat the load, the meter or the temporary-connection checks.
Water is a connection, a borewell or a tanker, and the bills tell you which. The questions to ask are in our note on apartment water. A gas meter does not prove the sump is on BWSSB supply.
Take keys only after the occupancy checks you actually need. Our 25 checks before possession include the services you will live with. A finished kitchen is not the same as a building that was allowed to be occupied. An OC does not lay the riser. A riser does not create the OC.
LPG, where the survey says the main has not arrived, remains a cylinder connection with its own distributor. NoBroker's Indane note is that other guide. We are not rewriting it here. Do not pay a PNG deposit for a building the survey has not cleared, on the theory that the cylinder and the pipe are the same product. They are not. One is a bottle. The other is a metered network.
Checklist
Related reading
Frequently asked questions
On the PNGRB entity list opened on 8 Nov 2026, the row for Bengaluru Rural and Urban districts names GAIL Gas Limited. That is the authorisation we could see. It does not mean a main has been laid to every building in those districts. Ask for the feasibility survey at your address.
GAIL's procedure page says it is not charging for registration. It then lists security deposits before supply: ₹4,000 for the connection and ₹500 towards consumption, both described as refundable and interest free, and a separate line on a ₹1,000 reduction on the connection deposit. Confirm the payable amount on your application. Pay GAIL against a receipt.
Yes, unless your flat number is already on a GAIL registration in your name. A project claim can mean a shaft, a street main, or a plan to apply later. Ask for the application number or the business-partner number, and for the name on the meter. A transfer, except on death, is listed at ₹250.
The procedure page prices conversion from LPG to PNG at ₹50 a burner, and ₹300 for a four-burner stove with an oven and a grill. Conversion is not the same as activation. Wait until GAIL has fitted, tested and activated the supply.
You stay on a cylinder until a survey says a connection is feasible and the pipe is actually laid. Do not pay the PNG deposit to reserve a future main. NoBroker's Indane guide is about a cylinder connection. It is a different product from the metered pipe on this page.
No. BESCOM meters electricity. BWSSB, a borewell or a tanker supplies water. Keep those papers separate, and do the possession checks even if the kitchen already has a hob on the drawing.
Get a GAIL registration or business-partner number in your name, confirm the payable deposit on the application for this address, and confirm in writing that a riser route has been agreed for the building. Pay GAIL against a receipt. Do not hand cash to a site supervisor for "the gas deposit".
Paper note: Deposit figures are from GAIL Gas's published application procedure, which is not marked as a Bengaluru-only tariff. Confirm them on your application. This page is not a gas-safety certificate. Do not test an unactivated outlet. Checked 17 Nov 2026.
Sources
Checked 17 Nov 2026.
-
Petroleum and Natural Gas Regulatory Board, entity web links, opened 8 Nov 2026. The Karnataka row for Bengaluru Rural and Urban districts names GAIL Gas Limited and links to the company's Bengaluru operations page: https://pngrb.gov.in/eng-web/entity-weblinks.html and https://gailgas.com/operation/bengaluru
-
GAIL Gas Limited, application procedure. Registration: no charge. Security deposit lines: a ₹1,000 reduction on the connection security deposit; ₹4,000 refundable and interest free as connection security deposit before supply starts; ₹500 refundable and interest free towards gas consumption. Documents: identity proof, and ownership proof illustrated as a sale deed or agreement, rent agreement, electricity bill, BSNL bill or society certificate. Online registration at customer.gailgaspng.com generates an application number, then a business-partner number after document checks. Installation order: feasibility survey; MDPE after civic permissions; vertical piping to registered customers; fitting and testing of GI or copper pipe and meter; then stove conversion and activation. After-sales table includes name transfer except on death at ₹250; stove conversion at ₹50 a burner and ₹300 for a four-burner stove with oven and grill; internal pipe refit at ₹350 a metre subject to a ₹500 minimum; disconnection and reconnection at ₹100 each. The page is not labelled as a Bengaluru-only tariff: https://gailgas.com/products/application-procedure
-
NoBroker, Indane new-connection note. This is an LPG cylinder guide. It is listed because buyers searching for a new-flat gas connection land on it. No charge, deposit or Bengaluru PNG rate was taken from it: https://www.nobroker.in/blog/indane-gas-new-connection/