Cement Calculator

Bags of cement, sand and aggregate for your work.

Your inputs

Work and size
Work
ft
ft
mm
per bag
Adjust mix, factors and bag size
part
parts
parts
×
kg
%

Changing the work type resets the mix, factor and thickness to its usual values.

Your result

Indicative
Cement bags
19 bags

50 kg bags for 2.79 m³ of concrete at 1:2:4.

45.5 cu ft
Sand
90.9 cu ft
Aggregate
₹ 7,220
Cement cost
2.79 m³
Volume of work
For slabs, beams and columns, use the mix your structural engineer specifies. Includes 5% for wastage.

Quick answer: Cement = wet volume × dry volume factor × the cement share of the mix, at 1,440 kg per m³. A 20 × 10 ft slab 150 mm thick in 1:2:4 concrete is 2.79 m³ and needs 19 bags of 50 kg with 5% wastage, plus 45 cu ft of sand and 91 cu ft of aggregate.

Quantities, step by step

Updates as you type
From your dimensions, mix and factors. Cement taken at 1,440 kg per m³.
ItemValue
Volume of work2.787 m³ (98.4 cu ft)
Wet mix volume2.787 m³
Dry materials, with wastage4.507 m³
Mix (cement : sand : aggregate)1:2:4
Cement927 kg
Bags19 (18.5 exact)
Sand1.288 m³ (45.5 cu ft)
Aggregate2.575 m³ (90.9 cu ft)
Cement cost₹ 7,220

How do you use the cement calculator?

  1. Pick the work: concrete, brickwork or plaster. The usual mix and thickness fill in.
  2. Enter the length and the width (or height, for a wall) in feet, the thickness in millimetres and the price of a bag.
  3. Read the bags of cement and the sand and aggregate. Change the mix, dry volume factor, bag size and wastage under “Adjust mix, factors and bag size”.

How is cement worked out from a mix ratio?

A mix such as 1:2:4 gives the parts of cement, sand and aggregate by volume. Wet concrete or mortar takes up less space than the dry materials that go into it, because the sand fills the gaps between the stones and the cement fills the gaps in the sand. Site estimates allow for this with a dry volume factor, commonly 1.54 for concrete and 1.33 for mortar. The cement’s share of the dry volume is then converted to kilograms and bags.

For brickwork, the bricks take up most of the wall and the mortar only fills the joints. The calculator takes mortar as 25% of the wall volume, a common rule of thumb you can change; counting the whole wall as mortar would overstate the cement about four times (25 bags instead of 7 for a 20 × 10 ft wall).

How the quantities are worked out

1
Wet volumeLength × width × thickness (× mortar share, for brickwork)
2
Dry volumeWet volume × dry volume factor × (1 + wastage %)
3
CementDry volume × cement parts ÷ total parts × 1,440 kg per m³ ÷ bag size, rounded up
4
Sand and aggregateDry volume × their parts ÷ total parts

Worked example: 20 × 10 ft slab, 150 mm thick

The slab holds 2.79 m³ of concrete. At 1:2:4 with a 1.54 dry factor and 5% wastage, it needs 927 kg of cement, or 19 bags of 50 kg (₹ 7,220 at ₹ 380 a bag), plus 45.5 cu ft of sand and 90.9 cu ft of aggregate.

Worked example: plastering a 12 × 10 ft wall

A 12 mm coat of 1:4 plaster on 120 sq ft is 0.134 m³. With a 1.33 dry factor and 5% wastage it needs 1.1 bags, so you buy 2, and 5.3 cu ft of sand.

How much cement per cubic metre?

Per 1 m³ of finished concrete or mortar, before wastage, using the default dry volume factors.
Mix50 kg bagsSand, cu ftAggregate, cu ft
Concrete 1:2:46.3415.531.1
Concrete 1:1.5:38.0614.829.7
Mortar 1:65.4740.30.0
Mortar 1:47.6637.60.0

What should you check on site?

Frequently asked questions

At a 1:2:4 mix with a dry volume factor of 1.54, one cubic metre of concrete needs about 6.3 bags of 50 kg before wastage. A richer 1:1.5:3 mix needs about 8.1. The table on this page lists both, along with mortar mixes; use your engineer’s mix design for structural work.

Dry cement, sand and aggregate shrink in volume once mixed with water, because the finer materials fill the gaps in the coarser ones. Estimates scale the wet volume up to find the dry materials needed. Site practice commonly uses 1.54 for concrete and 1.33 for mortar; you can change it.

Only the mortar in the joints uses cement. The calculator takes the mortar as 25% of the wall volume, a common rule of thumb, then applies the mix ratio. For a 20 × 10 ft wall 230 mm thick at 1:6, that is about 7 bags. Check the figure with your mason or engineer.

Mixes such as 1:4 and 1:6 are common on site, usually with a coat around 12 mm thick, and the calculator starts at 1:4. These are conventions rather than rules, so follow what your engineer or contractor specifies for your walls and the finish you want.

Cement is sold by the bag, and running short mid-pour can spoil the work. The bags figure is rounded up after adding wastage. The table on this page shows the exact number as well, so you can see how much is left over.

No, only cement. The page gives the volumes of sand and aggregate so you can ask your supplier for prices, which vary with the material and the delivery distance. Labour and machine charges depend on your contractor. GST on materials depends on the bill.

Sources

Indicative quantities for planning, not a structural design. For structural work, follow your structural engineer’s drawings. For GST on materials, indicative only.

Building or extending a home in Bengaluru? Talk to an acre&key advisor.

Related calculators

The next steps most buyers take after this one.

Construction Cost Calculator
Cost to build a house from a contractor quote and the extras it leaves out.
Calculate →
Steel Calculator
Reinforcement steel in kg and bars, from your engineer’s figure.
Calculate →
Brick Calculator
Bricks and mortar for a wall.
Calculate →
Tile Calculator
Tiles and boxes for a room, priced on the boxes you buy.
Calculate →
Paint Calculator
Litres of paint and cans to buy for your walls and ceiling.
Calculate →
Renovation Cost Calculator
Add up the cost of redoing an existing flat, room by room.
Calculate →