How to read a Karnataka RERA quarterly progress report before the next installment

The terminal building and a service road at Kempegowda International Airport, Bengaluru

Photo: Pinakpani, Wikimedia Commons.

RERA COMPLIANCE 8 min read Updated November 2026

Under Section 11(1) of the Real Estate (Regulation and Development) Act, 2016, promoters of registered Karnataka developments are legally required to upload a Quarterly Progress Report (QPR) on rera.karnataka.gov.in within 15 calendar days from the close of each quarter. The QPR serves as an audit tool for buyers before authorizing construction-linked loan disbursements. It details floor-by-floor physical progress percentages, geo-tagged site photographs, inventory booking counts, statutory approvals obtained/pending, and RERA escrow account health. Comparing the filed QPR against developer demand notes prevents paying for uncompleted structural milestones.

When purchasing an under-construction apartment in Bengaluru, homebuyers are routinely confronted with developer payment demand notes. These notices often assert that structural milestones—such as the "12th Floor Slab" or "Internal Plastering"—have been achieved, accompanied by strict 15-day payment deadlines and threats of 18% delayed-payment interest.

Many buyers hurriedly authorize bank loan disbursements based solely on computer-generated demand letters and promotional marketing emails.

However, under Karnataka RERA mandates, every registered promoter must submit quarterly operational disclosures under penalty of law. Learning how to navigate and dissect a Karnataka RERA Quarterly Progress Report (QPR) provides homebuyers with verifiable, regulatory evidence to validate payment demands before releasing capital.

The statutory basis of the Quarterly Progress Report

Under Section 11(1) of the RERA Act, 2016 and Karnataka RERA Rules, promoters must maintain a public project webpage and update critical data fields every 90 days:

+--------------------------------------------------------------------------------+
|                 KARNATAKA RERA QPR DISCLOSURE CYCLE                            |
+--------------------------------------------------------------------------------+
|  [QUARTER TIMELINE]                                                            |
|  Q1: Jan-Mar | Q2: Apr-Jun | Q3: Jul-Sep | Q4: Oct-Dec                         |
|                                                                                |
|  [STATUTORY FILING DEADLINE]                                                   |
|  Within 15 days following quarter close (e.g., Q1 filed by April 15)           |
|                                                                                |
|  [MANDATORY DISCLOSURE CATEGORIES]                                             |
|  1. Building-by-building & floor-by-floor physical completion percentages      |
|  2. Geo-tagged date-stamped photographic evidence per wing & tower             |
|  3. Sold vs unsold inventory counts (Apartments, Plots, Parking Bays)          |
|  4. Status of pending approvals (Airport NOC, Fire NOC, BWSSB, BESCOM, OC)     |
|  5. 70% Escrow Account utilization and Form 3 CA withdrawal certificates       |
+--------------------------------------------------------------------------------+

Step-by-step: how to access a project QPR on K-RERA

  1. Visit the Portal: Open the official portal at rera.karnataka.gov.in.
  2. Locate Project Search: Click on Services -> Project Status / Approved Projects.
  3. Search by Registration Number: Enter your project's K-RERA acknowledgment or permanent registration number (e.g., PRM/KA/RERA/1251/...). Always search using the official RERA registration number rather than marketing brand names.
  4. Access Project Details: Click on the project name to open the comprehensive project dashboard.
  5. Open Quarterly Progress Reports: Navigate to the Quarterly Updates tab and download the latest filed Form 1 (Architect), Form 2 (Engineer), and Form 3 (Chartered Accountant) submissions.

The 5-point audit framework before releasing installments

+--------------------------------------------------------------------------------+
|                 5-POINT QPR AUDIT FRAMEWORK FOR BUYERS                         |
+--------------------------------------------------------------------------------+
|  [CHECK 1: FILING CURRENCY]                                                    |
|  Is the latest quarter uploaded? A gap of 2+ quarters signals compliance stall.|
|                                                                                |
|  [CHECK 2: TOWER-SPECIFIC PROGRESS VS DEMAND]                                  |
|  Does the Form 2 Engineer percentage validate the slab demanded in your wing?  |
|                                                                                |
|  [CHECK 3: RECYCLED PHOTOGRAPHS]                                               |
|  Compare current photos against previous quarter. Has concrete work moved?    |
|                                                                                |
|  [CHECK 4: STATUTORY APPROVAL PIPELINE]                                        |
|  Are critical sanctions (Fire NOC, BESCOM, BWSSB, OC) applied for on schedule? |
|                                                                                |
|  [CHECK 5: FINANCIAL ESCROW RATIO]                                             |
|  Does Form 3 verify that 70% of collections were deposited and spent on site?  |
+--------------------------------------------------------------------------------+

1. Reconciling floor progress against the demand note

The most critical disclosure is the Engineer's Certificate (Form 2). This document breaks down physical completion by tower: - Earthwork / Excavation - Basements / Podiums - Number of Slabs Poured - Internal Brickwork & Plastering - MEP Services (Plumbing, Electrical Risers)

If your developer issues a demand note for the "14th Floor Slab," but the Form 2 filed on K-RERA certifies that the building has achieved only 9 slabs, an immediate red flag exists. Promoters cannot demand advances for milestones that have not been physically completed and certified.

2. Spotting recycled or deceptive site photographs

Under Karnataka RERA regulations, promoters must upload date-stamped, geo-tagged photographs showing each tower, wing, and common infrastructure asset (roads, STP, clubhouse).

Examine these photos closely: - Check weather indicators (e.g., overcast monsoon skies uploaded for a dry January filing). - Check construction equipment (e.g., the same crane position and unfinished shuttering across multiple quarters). - Verify internal finishing: Do internal photos show active brickwork and conduit laying, or bare concrete corridors?

3. Monitoring statutory approvals

The QPR splits municipal approvals into four categories: 1. Approvals already obtained (e.g., Plan Sanction, Fire Initial NOC). 2. Approvals applied for, with expected issuance dates. 3. Approvals still to be applied for (e.g., Final Occupancy Certificate, Lift Inspectorate). 4. Modifications or revisions issued by civic bodies.

If a project scheduled for delivery within 12 months still lists BWSSB water linkage or Fire Final Clearance as "yet to be applied for," handover will inevitably experience delays.

4. Reviewing inventory sales velocity

The QPR reveals exactly how many units have been booked versus remain unsold. - A high inventory absorption rate (80%+ sold) indicates strong developer cash flows. - A stalled sales velocity (under 40% sold in a maturing project) combined with lagging construction percentages signals potential working capital distress, requiring cautious scrutiny before releasing discretionary advances.

QPR pre-disbursement verification checklist

Perform these due diligence checks on the K-RERA portal before releasing loan tranches.

Frequently asked questions

Failing to upload quarterly updates within 15 days of quarter-end violates Section 11 of the RERA Act. Allottees can file a formal complaint with Karnataka RERA. The Authority possesses powers to levy penalties under Section 61 (up to 5% of total project cost) and freeze the developer's RERA account.

If a developer demands payment for a milestone that has not been certified on the K-RERA portal, the demand is legally premature. The buyer can reply in writing attaching the latest filed Form 2 showing the incomplete milestone. Under RERA model rules, buyers cannot be penalized with delayed-payment interest for disputing premature demands.

Form 3 is a statutory financial certificate issued by an empanelled Chartered Accountant. It audits the project's 70% RERA Escrow Account, certifying total buyer funds collected, land costs, actual construction expenditures incurred, and the permissible withdrawal ratio.

Yes. Under standard RERA contractual principles and Karnataka guidelines, allottees or their authorized representatives have the legal right to inspect construction progress at reasonable intervals, subject to site safety protocols.

Promoters must upload QPR disclosures four times per year—within 15 days following the end of each financial quarter (April 15, July 15, October 15, and January 15).

Legal Note: Construction milestone covenants and quarterly disclosure duties are strictly governed by the Real Estate (Regulation and Development) Act, 2016. Consult an empanelled real estate lawyer before issuing formal dispute notices to developers.

Technical Note: To verify complex engineering percentage disputes, consider engaging a licensed civil structural engineer to conduct a third-party site progress valuation.

Sources

Checked 18 Nov 2026.

  1. Real Estate (Regulation and Development) Act, 2016 (Section 11 - Functions and Duties of Promoter): https://rera.karnataka.gov.in/resources/staticpage/Real_Estate_Act.pdf
  2. Karnataka Real Estate (Regulation and Development) Rules (Quarterly Disclosure FAQs): https://rera.karnataka.gov.in/resources/staticpage/KARNATKA_FAQs.pdf
  3. Karnataka RERA Approved Project Portal: https://rera.karnataka.gov.in/